As part of ongoing efforts to maintain Cheyenne’s water and sewer systems, the City of Cheyenne Board of Public Utilities expects construction in the following areas during the upcoming week. This list consists of the projects that require traffic controls and may be of interest to motorists and customers. It is not intended as a summary of all water and sewer activitie:

East 10th Street – Closed to through traffic between Crook Avenue and Converse Avenue. Crook Avenue between East 9th Street and East 10th Street will also be closed. Purpose: Fire hydrant replacement. Expected Dates: 7/29/13 to 8/7/13

East 17th Street – Closed to through traffic between Big Horn Avenue and Campbell Avenue.Purpo e: Fire hydrant replacement. Expected Dates: 8/5/13 to 8/16/13

West 9th Street – Closed to through traffic between Snyder Avenue and Deming Drive. Purpose: Water main replacement.Expected Dates: 7/29/13 to 8/9/13

West Jefferson Road – Closed to through traffic between King Court and South Cribbon Avenue. Lummis Avenue between West Leisher Road and West Jefferson Road will also be closed.Purpose: Sewer manhole replacement and sewer line repairs.

Expected Dates: 8/5/13 to 8/23/13

 

Walterscheid Boulevard – Closed to through traffic between West Fox Farm Road and West Allison Drive. Local business and residential access is available.

Purpose: Street work following water main installation.

Expected Dates: 6/10/13 to 8/16/13

 

Walterscheid Boulevard – Closed between West Allison Drive and West College Drive.

Purpose: Water main installation.

Expected Dates: 7/12/13 to 8/16/13

 